For Vance Refrigeration Q#28, how do you calculate the total variable MOH with the information given? When I checked the answers, it did not specify how to get the spending variance = 1300F. The only variances that were given to us were the material quantity variance and direct labour variance.
ASA Academic Team Changed status to publish
Hi Karen,
It seems this question is missing the spending variance in the given information. For now, just assume that it is included as 1300 F.
Thanks for bringing this to our attention and good luck on your exam!
Alex
ASA Academic Team Answered question